As advanced air mobility (AAM) becomes a reality, the question on many people’s minds is where these aircraft will take off and land.The first wave of advanced air mobility (AAM) may depend less on building futuristic vertiports than on rethinking the aviation infrastructure already in place. Existing airports and fixed-base operators, or FBOs, offer a practical starting point for electric aircraft operations. They have ramps, passenger facilities, aviation expertise and customers. What they need next involves more than installing chargers: operators must secure electrical capacity, rethink passenger movements and align investment with demand. That message anchored “AAM Infrastructure: Preparing Airports and FBOs for Vertiports,” a panel at NBAA-BACE moderated by Mike French of Signature Aviation. Joining French were Filippo Giusti of UrbanV, Bryan Bernhard of Archer, Scott Cutshall of Clay Lacy Aviation and Nate Ward of Beta Technologies.
Why Existing Airports Should Lead AAM Infrastructure Development

Panelists agreed that AAM should begin where aviation already operates, rather than depend on an entirely new network of dedicated facilities.
Bernhard described existing airports as the industry’s backbone. Archer’s proposed Los Angeles-area network illustrates that approach, connecting established aviation locations to destinations where travelers might otherwise face lengthy drives.
Giusti made the financial case for starting at FBOs. Existing terminals, established brands and customer relationships give developers a foundation for testing demand before committing to larger facilities. Giusti’s company, UrbanV, envisions a phased progression: initial airport-to-airport operations with limited aircraft availability and high prices, followed by dedicated airport infrastructure and early off-airport connections. A denser transportation network would come later.
The challenge lies in timing investment. “If we build today for tomorrow’s scale, we risk overbuilding,” Giusti said. Waiting until that scale arrives creates the opposite risk, that infrastructure may not keep pace. His solution is to: start early at FBOs, start small with a charging-equipped stand, and preserve room to expand.
Airport Electrification Starts With Power Planning

For airports and FBOs considering electric vertical takeoff and landing aircraft (eVTOLs), the first infrastructure question concerns the power supply, not the appearance of a future vertiport.
Cutshall said Clay Lacy began evaluating electric aviation because its Van Nuys and Orange County FBOs sit within a prospective launch market. The company approached electricity as another fuel offering, while recognizing that electrical infrastructure requires different planning. “The way we look at it is that electricity is just another type of fuel,” he said.
Determining capacity proved more complicated. Charging one aircraft creates a different requirement than charging several simultaneously. In the early planning stages, Cutshall said, neither the aircraft industry nor utilities could provide every answer.
Giusti urged operators to investigate power availability early. Depending on the state, he said, bringing power to a site could take six to 18 months.
Preparation does not require an immediate charger purchase, according to Ward. Airports can begin by discussing electrical service, reviewing their airport layout plans and identifying how charging would fit into future capital improvements. That approach gives operators a way to prepare without making every investment before aircraft demand materializes. It also creates an opportunity to incorporate electrical work into planned ramp projects rather than revisit the same ground later.
Designing FBO Ramps for Fast eVTOL Turnarounds

Electric air taxis could introduce an operating rhythm unfamiliar to many FBOs. Cutshall contrasted aircraft that remain overnight with a future air taxi model targeting roughly 12 to 15 minutes on the ground. That short stop must accommodate passenger unloading, boarding and charging.
Clay Lacy’s Orange County redevelopment offered a practical example of how those requirements influence ramp design. Aircraft partners wanted to taxi into and out of charging positions rather than hover into place, Cutshall said, because hovering consumes more electricity. They also wanted to avoid towing during brief turnarounds.
Passenger access mattered just as much. Clay Lacy sought charging positions close to both the taxiway and passenger terminal, reducing the need to escort travelers through a busy ramp. “Every 15 minutes you don’t want to be walking four passengers through a maze of airplanes,” Cutshall said.
Those decisions connect aircraft efficiency to staffing and safety. A charging position that looks convenient on a site plan may create operational problems if passengers must cross active aircraft areas or employees must repeatedly leave other duties to escort them.
Why Shared Aircraft Charging Standards Matter
Panelists also argued that infrastructure should support multiple aircraft manufacturers. Bernhard said Archer wanted to avoid the fragmented charging experience that emerged during the early growth of electric vehicles. He described collaboration with Beta and other infrastructure participants around CCS charging, with the goal of allowing a single installation to serve more aircraft types. “We want to try and install this one time, do it right and have access to as many aircraft as possible,” Bernhard said.

The companies also discussed their work through the America’s Consortium for Electric Skyways (ACES) coalition to coordinate infrastructure planning and investment. Bernhard said the initiative brings Beta and Archer together to discuss deployment plans and provides a platform for public and private stakeholders to engage on capital investment. Ward described its practical focus, to bring demand signals together around infrastructure projects that participants can actually put in the ground.
For FBOs, that coordination could help address a difficult investment question: how much capital should they commit to electrical service, trenching and charging equipment before certified aircraft arrive? Cutshall said those discussions already involve exploring mutually beneficial ways to prepare facilities and launch operations.
Ward described Beta’s charging equipment as part of a broader operating system. High-tempo service requires both charging and battery thermal management, he explained, because batteries heat during charging and operators must manage their temperature. Lower-tempo locations may need a different solution. He described a smaller, portable charging product for applications such as developing markets or diversion locations.
The distinction reinforces the panel’s investment message: infrastructure should match the intended operation as well as the weather and temperature characteristics of the region. A location supporting occasional flights does not necessarily need the same equipment as a high-frequency air taxi hub.
Passenger Throughput Could Reshape the FBO Business
Charging aircraft represents only part of the infrastructure challenge. Moving passengers quickly enough to preserve an air taxi’s time advantage could prove equally consequential.
Cutshall outlined the operating assumptions behind a potentially dramatic increase in FBO traffic: departures every 15 to 20 minutes, carrying three or four passengers, across a 12-hour operating day. With two aircraft positions, he estimated annual throughput could reach 60,000 to 70,000 passengers, a volume and cadence traditional FBOs are not prepared to handle without changes. “If this industry achieves what it’s going for, the traditional FBO is going to struggle with that passenger throughput,” Cutshall said. “And FBOs are not used to that high passenger cadence.”
That scenario raises questions about identification checks, passenger and baggage weights, staffing, waiting areas and ground transportation. “You don’t want to have a 15-minute flight that you’re paying for and then you waste 20 minutes waiting for the airplane,” Cutshall said.
Bernhard said Archer intends to prepare customers through an app before they arrive, including information about their journey and safety preparation.
French described a broader end-to-end transportation concept in which travelers coordinate ground transportation, the flight and the final leg through a connected service. That model could also help address an audience member’s concern about parking demand at space-constrained airports.
But the panel did not suggest that technology alone resolves those challenges. FBOs will still need to plan how people move through their facilities and reach aircraft without creating bottlenecks.
Preparing for AAM Without Overbuilding Vertiports
The panel’s final advice paired urgency with restraint, in a closing lightning round:
- Airports must understand their power situation and begin discussions with infrastructure partners, while avoiding large dedicated vertiport investments without sufficient demand or aircraft availability, according to Guisti.
- Bernhard encouraged early planning and collaboration rather than isolated development.
- Cutshall called on airports to approach their FBOs proactively and ask how they could help introduce the technology.
- Ward pushed back against the assumption that electric aviation applies only to major metropolitan air taxi routes. He pointed to medical, cargo and other applications that could broaden the role of existing community airports.
For business aviation, the opportunity lies in adapting an established network to new aircraft and service models. The immediate task is not to build the largest possible vertiport, but rather to establish where a useful service can work, prepare the power and ramp infrastructure and expand as operations justify the investment.